WORK IN PROGRESS Read more: Newlyn's small boat pontoons >>
Pontoons Material will be dredged at the Harbour and be taken by lorries along the back by the boat repair slip and out through Sandy Cove. Working hours will be 7.00am to 7.00pm although it is unlikely that all those hours will be worked. The order for the pontoons has been placed and they are being manufactured. It is anticipated that the drilling rig for the placing of the piles supporting the pontoons will be commencing mid February. This work will take about 2 months. It is anticipated that the scheme will be completely finished on the 30th of June.
Electricity will be connected at the 2nd of February and the fridge motors
will be commissioned shortly afterwards. Keel Alley has been dug up to
relay the new cables serving the new equipment at the Fish Market.
also see introduction>> reports>> |
![]() |
|
![]() |