also see introduction>> reports>> WORK IN PROGRESS
Pontoons Material will be dredged at the Harbour and be taken by lorries along the back by the boat repair slip and out through Sandy Cove. Working hours will be 7.00am to 7.00pm although it is unlikely that all those hours will be worked. The order for the pontoons has been placed and they are being manufactured. It is anticipated that the drilling rig for the placing of the piles supporting the pontoons will be commencing mid February. This work will take about 2 months. It is anticipated that the scheme will be completely finished on the 30th of June.
also see introduction>> reports>> |
![]() |
|
![]() |